Sunday, December 31, 2006

Moving on to second floor!

Left: Kim is drilling and securing the second floor platform of the room.

"Officially" we started the work on the second floor. Drilling and securing the platforms.

Hmm, the steel cutter's blade was worn out today. The diameter of the blade was grinded to very small such that it is not enough to cut thru the mild steels. Tomorrow and Monday is holiday, so I guess we can’t do any mild steel cutting until new blade arrives.

Anyway, our mild steels also almost finished, only left two. We need more mild steels for the supporting beams of the center structure. Guess it’s quite hard to do things when u have limited budget.

Hmm, I can tell that our progress there few days were faster. But manpower is still a problem. Luckily today, KR “National Welder”, Hoong Soon*, came down to help us. Ha, huge difference between me and We Liam’s speed of welding with him.

*Hoong Soon: Stage Crew (2006), Rag (2006), Chingay (2007). Got this “National Welder” nickname because his skill in welding. ;)

No comments: